68th Street Dump Superfund Site

GOVERNMENT

68th Street Superfund

Landfill closure in Baltimore

Project Details

Market

Government

Location

Baltimore, Maryland

Project Partners

Entact Environmental (contractor), Presto Geosystems (design and manufacturer)

Construction Timeline

2024

Our Scope

GEOWEB® supplier and site support

About the Project

The 68th Street Dump encompasses a 239-acre area and encompasses multiple landfills. After accepting industrial and commercial waste for years, the site was recently designated as a Superfund site, necessitating a comprehensive remediation strategy.

GEOWEB® for Landfill Cap

51,000 square feet of the landfill (all slopes steeper than 3:1) was capped using GEOWEB® GW30V 12-inch depth geocells, infilled with topsoil.

GW30V12 was the perfect solution to the site because it isolated the hazardous material, ensured compliance with the EPA’s 12-inches of cover requirement, successfully managed the steep and complex topography, and provided a durable solution that could provide lasting erosion protection against environmental conditions.

Benefits of GEOWEB® for Landfill Caps

3D system stabilizes the steep slopes, preventing erosion.

Pre-assembly and ATRA® systems improves installation and connection.

Topsoil filled cells create environment for sustained vegetation, improving aesthetic and ecological value.

Government Services

Related Projects

Permanent cap for Virginia Beach Landfill

Landfill closure

Virginia Beach Landfill

Franklinton Landfill

Landfill Closure

Franklinton Landfill

Let’s Get to Work

Contact our team to get started with a quote.

Scroll to Top